Construction of the Msalato International Airport in Dodoma has entered its final phase, with the infrastructure package 89 per cent complete and the buildings package 78 per cent complete.
Tanzania National Roads Agency (TANROADS) Chief Executive Engineer Mohamed Besta told journalists at the project site on Thursday that infrastructure works were scheduled for completion by November while the buildings were expected to be completed by December.

He said TANROADS was closely monitoring contractors’ work programmes, equipment delivery and installation, and coordination of interdependent activities to ensure the remaining works were completed on schedule.

The project, being implemented by the government in collaboration with the African Development Bank (AfDB), is intended to strengthen Tanzania’s air transport infrastructure and increase passenger and cargo handling capacity.

It is also expected to provide Dodoma with a modern international airport capable of supporting domestic and international air services while creating opportunities for trade, investment, tourism, cargo transportation and employment. Eng Besta said the first phase was being implemented through two packages covering infrastructure and buildings.

As of this week package one had reached 89.02 per cent completion, with the runway 98 per cent complete and taxiways and aircraft apron each at 99 per cent. The access and internal roads and vehicle parking areas were 75 per cent complete, while the water supply system stood at 89 per cent.

Diramakini

DIRAMAKINI is Tanzanian news media house established to play role in shaping the global agenda through telling true stories by delivering quick and in-depth.Our readers trust our coverage of the issues that matter most to them. Our agenda-setting journalism attracts. Contact us on diramakini@gmail.com OR +255 719 254 464.

Post a Comment

Previous Post Next Post

Know matter how large or small your business is, advertising here